A useful pump RFQ defines the required operating cases, fluid, suction conditions, installation, power supply, and delivery scope before asking for a model and price. RFQ means request for quotation. The specification sheet should tell suppliers what the equipment must do and identify the information they must return to support their offer. For a slurry pump, flow and head alone are insufficient. Solids characteristics, concentration basis, material compatibility, source conditions, and operating variability can affect the selection. Missing information should remain visible as an open item instead of becoming an undisclosed supplier assumption. This guide focuses on complete pump procurement, including optional drivers and package equipment. It is separate from a replacement-part inquiry based on an existing part number or drawing. The framework combines established pumping principles with editorial purchasing guidance; the worked RFQ is fictional and is not a Longteng performance claim.

What should the first page of a pump inquiry establish?
Identify the application, equipment tag, required quantity, service location, and project contact. Explain whether the purchase is for a new installation, an equipment replacement, or an expansion of an existing process. That context helps the supplier understand which interfaces are fixed and which can change.
State the intended supply boundary early. A bare pump, a pump and motor, and an assembled package are different commercial requests. If you want alternatives, label them as separate options rather than allowing each supplier to choose a different base scope.
Give the proposal due date and desired delivery milestone, while identifying dependencies such as drawing approval or availability of process information. Ask the supplier to state its schedule assumptions. A date without a defined starting event or approval requirement is difficult to compare across offers.
Name the person who can answer process questions and the person who can approve commercial changes. A coordinated inquiry does not require every decision to pass through one specialist, but it should keep technical and commercial revisions connected to the same equipment requirement.
How should flow and head be specified?
Provide flow and total dynamic head together for each required operating case. Total dynamic head is the energy per unit weight the pump must add across the defined system boundary. It includes the relevant elevation, pressure, velocity, and loss terms; it is not simply the vertical lift.
Identify a normal duty and the other meaningful cases, such as low source level, maximum throughput, or operation through a different pipeline route. Pair each flow with the corresponding required head and source conditions. Independent maximum flow and maximum head values can describe two different situations rather than one valid duty point.
State whether the head comes from a system calculation, measured operating data, or a preliminary estimate. Supply the system curve or calculation assumptions where available. A supplier can then distinguish a firm requirement from a value that still needs engineering review.
Use consistent units and identify whether flow refers to the whole mixture or another quantity. For slurry, a solids production rate is not automatically the mixture volumetric flow required for hydraulic selection. Provide the conversion basis, concentrations, and densities if the supplier is expected to derive the mixture flow.
What fluid information belongs in the specification sheet?
Describe the liquid phase, solids, chemistry, and temperature range. For solids, provide a representative particle-size distribution and note coarse particles, sharp particles, fibers, debris, or other features relevant to transport and wear. A single average size can conceal the larger particles that affect passage requirements.
State whether solids concentration is by mass or by volume, and identify the associated density information. These bases are not interchangeable. Explain whether the supplied values are normal, limiting, measured, or estimated so the application review can account for uncertainty.
For viscosity, give the temperature and measurement basis. If the material is non-Newtonian, meaning its flow behavior cannot be represented adequately by one constant viscosity under all conditions, provide relevant rheological data or identify the need for further evaluation. Do not reduce a complex mixture to a convenient water-like assumption.
Describe entrained air, froth, gas release, settling, or intermittent feed where relevant. These conditions can change the suitability of a pump arrangement and the interpretation of liquid-only calculations. The inquiry should make them explicit instead of relying on the word slurry to communicate every difficulty.
RFQ field | Information to provide | Why the distinction matters |
Operating cases | Paired flow and head, duration, and source conditions | Prevents unrelated maximum values becoming a false duty |
Mixture properties | Density, concentration basis, liquid and solids description | Establishes the medium being selected and powered |
Particle information | Distribution, maximum relevant size, shape, debris | Supports passage and wear review |
Temperature and chemistry | Normal and limiting conditions with known constituents | Supports material and seal compatibility review |
Gas and feed behavior | Aeration, froth, settling, interruptions | Identifies conditions a simple liquid calculation may miss |
Data confidence | Measured, calculated, estimated, or unknown status | Makes selection assumptions reviewable |
Which suction conditions must be supplied?
Identify whether the pump draws from an open tank, pressurized vessel, sump, or another source. Supply normal and minimum liquid levels relative to a clearly named elevation reference. For an open source, site elevation or the applicable atmospheric pressure basis may be needed for suction calculations.
Provide liquid temperature, vapor-pressure information where relevant, and the suction-line arrangement. Pipe internal diameter, length, fittings, valves, strainers, and inlet conditions affect losses. A short line can still have a significant restriction, so length alone is not an adequate description.
NPSH means net positive suction head. Available NPSH comes from the installation and fluid; required NPSH is supplied for the pump under stated conditions. The buyer and supplier should agree who calculates the available value, how the required data are interpreted, and how the necessary margin is assessed.
For a vertical sump arrangement, also provide the installation depth, liquid-level range, inlet position, and relevant sump geometry. Immersion length, submergence, and available NPSH describe different things. A single depth dimension should not be expected to establish all three.
How much piping information should accompany the RFQ?
A simplified process or piping sketch can be more useful than several unconnected dimensions. Show the source, destination, pump location, reference elevations, major restrictions, control valves, and alternate operating routes. Label whether destination pressure is atmospheric, controlled, or variable.
If the project engineer has calculated the system curve, supply the curve and its assumptions. If not, provide enough information for the responsible party to identify the calculation scope. Do not ask the pump supplier to guarantee an unspecified piping system while withholding the information needed to evaluate it.
For an existing installation, include measured flow, suction and discharge pressures, speed, and measurement locations when reliable data are available. Identify gauge or absolute pressure and the liquid conditions. Readings taken at different times or operating states should not be combined into a fictional single point.
Describe planned changes such as pipe enlargement, a longer discharge route, different source levels, or additional equipment. Replacing a pump with the same nominal size may not reproduce the old duty after the system changes. The RFQ should reflect the intended future installation rather than only the retired nameplate.

What electrical and drive information is necessary?
State supply voltage, frequency, phase, and relevant site electrical requirements. Frequency is particularly important when comparing offers based on different speeds. Ask the supplier to identify the proposed motor, pump speed, transmission arrangement, and control method rather than assuming they follow from the pump model.
Explain whether a variable-frequency drive, or VFD, is required, available from the buyer, or proposed as an option. Define the required operating cases and control objective. A VFD changes speed but does not remove the need to check power, suction conditions, acceptable operating range, and the system's response.
Request the estimated absorbed pump power at the relevant duties and the basis for selecting the driver rating. The motor's nameplate output rating is not a prediction of actual electrical consumption. Energy comparisons need consistent boundaries, efficiencies, operating points, and operating hours.
Identify environmental conditions relevant to the motor and controls, such as indoor or outdoor installation, ambient temperature, altitude, washdown, and any specified area classification. Require the applicable proposal and documentation to be confirmed. Do not infer special electrical suitability from a general industrial product description.
Which installation and maintenance constraints affect the offer?
Provide connection details, orientation requirements, foundation or support information, and the available footprint. For a replacement, verify the actual interfaces instead of relying only on a model name. An old installation may have modified pipework, adapters, or baseplate dimensions that differ from the original catalog.
Show maintenance access, lifting restrictions, and removal paths. A pump that fits during installation may be difficult to service if the wet end or drive cannot be withdrawn. Ask for an outline drawing and the maintenance space required by the proposed configuration.
For slurry duty, describe access to wear components and any limits on shutdown duration. Request a recommended initial spare list with clear part identification and material. Treat the recommendation as a proposal to review against operating experience and criticality, not a universal replacement interval.
State who supplies foundations, pipe supports, utility connections, installation labor, alignment, and commissioning activities. These interfaces often sit outside the bare-pump quotation. Explicit assignment helps prevent a complete package from being interpreted as a complete installed pumping system.
How should the supply boundary be written?
Use an inclusion and exclusion schedule. Identify each significant item and require the supplier to state whether it is included, optional, buyer-supplied, or excluded. Keep the base offer consistent across suppliers and price alternatives separately.
The schedule should cover the pump, driver, transmission, base, guards, seals or packing arrangement, instruments, controls, documentation, initial spares, and any agreed services. Include auxiliary requirements where applicable, such as seal-support utilities, without assuming every pump design uses the same arrangement.
Scope item | Required RFQ response | Clarification to retain |
Pump and wet end | Model, configuration, materials, accepted duty | Applicable curve and wear-component identities |
Driver and transmission | Included equipment, rating, speed, control basis | Electrical supply and operating envelope |
Base and interfaces | Assembly boundary and outline drawing | Foundation, piping, lifting, and removal responsibilities |
Auxiliaries and controls | Itemized included and excluded equipment | Utility requirements and control integration |
Inspection and documents | Proposed activities and deliverable list | Acceptance basis, witnessing, and release conditions |
Spares and services | Separate quantities, scope, and commercial terms | Installation support and future reorder information |
Ask for a consolidated deviation list. An exception buried in a footnote or separate email can be missed during award. The final accepted offer should show which differences were resolved, which were accepted, and which remain outside the purchase.
What inspection and acceptance requirements should be included?
Specify the evidence needed to approve and accept the equipment. This may include an outline drawing, materials information, inspection results, hydraulic test data, operating instructions, and an order-specific parts list. Match the document requirement to the purchase instead of requesting every possible certificate by habit.
Where performance testing is required, define the test boundary, proposed method or standard, acceptance criteria, reporting, and any witnessing. ISO 9906's public scope concerns hydraulic acceptance testing for rotodynamic pumps with liquids behaving like clean, cold water. A reference to it does not by itself validate abrasive wear life.
Distinguish required test results from application predictions. If the supplier proposes corrections or interpretation for the process fluid, ask for the stated basis and limitations. A clean-water curve can be useful input without being represented as direct measurement on your slurry.
Agree on approval and release stages before production. State which drawings require buyer approval and which records must be submitted before shipment. Allow the supplier to identify cost or schedule effects during quotation, so acceptance requirements do not arrive as a late surprise.
What does a practical fictional RFQ example look like?
Consider a hypothetical plant transferring a characterized slurry between two process locations. Its engineer provides two calculated duties: a normal case of 100 m³/h at 35 m total dynamic head, and a lower-throughput case of 80 m³/h at 30 m. These are paired cases supplied for the example, not points from a manufacturer curve.
The inquiry states that mixture density is 1,300 kg/m³ at the normal condition and includes a separate fluid report identifying concentration basis, particle distribution, chemistry, and temperature. Those supporting data are essential. Density alone does not establish material selection, slurry performance correction, or maximum particle acceptance.
The plant supplies a suction sketch with level references and line details, a destination-pressure basis, and a requirement for a motor suitable for its specified 50 Hz supply. It requests an assembled pump-and-motor package, while the plant retains responsibility for foundations, piping, and electrical installation.
The supplier is asked to return a marked curve, proposed speed and materials, power assessment for both cases, suction review, outline drawing, inspection proposal, and explicit deviations. Until those responses are reviewed, the example does not establish a selected pump size or an acceptable model.
How should quotations be compared after they arrive?
Check that every offer addresses the same operating cases and medium description. Confirm the selected configuration and curve basis before comparing efficiency or power. A proposal at a different speed, impeller arrangement, or fluid basis may require clarification before its numbers are comparable.
Then compare the supply schedule and acceptance requirements. Identify missing equipment, excluded documents, optional tests, and services priced separately. Normalize the commercial totals only after the technical and scope differences are visible; otherwise, the lowest price may simply describe less equipment.
Review question | Acceptable evidence to seek | Issue requiring clarification |
Does the selection cover the stated cases? | Marked curve and operating-envelope explanation | Only one unrelated catalog maximum is quoted |
Are medium assumptions consistent? | Accepted fluid data and stated correction basis | Water-like behavior is assumed without disclosure |
Is the package complete to the requested boundary? | Itemized supply schedule | Motor, guards, or controls remain ambiguous |
Can acceptance be demonstrated? | Agreed inspection and test proposal | A generic tested statement replaces the required record |
Are deviations closed? | Consolidated accepted exceptions | Conflicting conditions remain in separate documents |
Evaluate operating cost over a stated schedule if energy is a selection criterion. Use the expected hours at each duty, a consistent electrical-input boundary, and the applicable energy price. Keep uncertain utilization separate from verified equipment data. A single efficiency value at an attractive point does not establish the annual consumption of a pump that spends much of its time elsewhere on the curve.
Maintain a clarification register until award. When an answer changes the equipment or scope, request an updated technical offer and price where necessary. The purchase order should refer to the final agreed revisions rather than a mixture of an early quote and later informal answers.
Frequently asked questions
Can I send an RFQ before every process value is known?
Yes, if you identify the missing values and request a preliminary response. State which assumptions may be used and which decisions remain open. A budget quotation based on incomplete data should not silently become a final manufacturing release without reviewing the missing information and its effect on the selection.
Should I specify a model or only the required duty?
For a new duty, provide the requirements and allow a supported proposal. For a controlled replacement, include the existing identity and interfaces, but still describe the actual service. If a particular model is mandatory, explain whether alternatives are permitted and how deviations should be presented.
Is motor power enough information to replace a pump?
No. The same motor rating can be associated with different pump curves, speeds, fluids, and duties. Supply the existing equipment identification, operating data, system conditions, and replacement objectives. The supplier needs a hydraulic and mechanical basis, not only a driver size.
Should the RFQ include a spare-parts package?
Include it when startup or maintenance planning requires it, and ask for itemized options if quantities are uncertain. Identify the equipment configuration and material associated with each spare. Separate consumables and wear components from unrelated accessories so the buyer can assess what each proposed item supports.
How should future capacity be described?
Provide a separate future operating case with its expected system conditions and timing. Ask whether the same configuration can support it and what changes would be required. Avoid adding an unexplained percentage to both flow and head, which can create an unrealistic selection and obscure the actual expansion plan.
Can I request both horizontal and vertical alternatives?
Yes, if the installation information allows a meaningful comparison. State the source geometry, available levels, space, maintenance access, and constraints. Ask each option to identify necessary installation changes. The alternatives should be evaluated as complete arrangements rather than two bare-pump prices for incompatible layouts.
What if two suppliers use different units?
Convert quantities to a common basis while preserving the original data and definitions. Confirm whether pressure is gauge or absolute, whether flow is mixture volume, and whether concentration is by mass or volume. A correct numerical conversion cannot fix a mismatch in what the quantity represents.
What should change after the preferred supplier is selected?
Resolve open assumptions, approve the accepted configuration and scope, and identify the governing document revisions. Transfer inspection, documentation, and delivery conditions into the order. Selection of a supplier should begin controlled execution of the agreed requirements rather than leave the quotation's unanswered questions for production to solve.
Send a complete inquiry for a supported proposal
Use the framework to assemble one controlled package: operating cases, medium data, source and system information, site and power requirements, supply schedule, and acceptance expectations. Label uncertain inputs and request a clear deviation list.
For a duty within the published horizontal or vertical slurry pump range, send the RFQ to Longteng Pump. Ask for a configuration-specific proposal and the supporting information needed to review selection, interfaces, scope, and acceptance before ordering.
Sources and What They Support
- U.S. Department of Energy: Improving Pumping System Performance — Supports the system approach to pump selection, operating duty, fluid effects, controls, and energy evaluation.
- Hydraulic Institute: Pump System Fundamentals New Industry Professionals Should Know — Supports the distinction between pump and system requirements and the need to evaluate operating and suction conditions together.
- ISO 9906: Rotodynamic Pumps—Hydraulic Performance Acceptance Tests — Supports the discussion of hydraulic test scope and why a test standard reference must be connected to an agreed acceptance requirement.